Facility Project Schedule

The Washington County Public Schools Facility Project Schedule is dynamic. Projects and schedules are adjusted periodically due to changes in academic programming, demographics, and specific facility challenges. We encourage you to review the facility schedule and offer suggestions on how better to serve the children and residents of Washington County, Virginia.

Capital Improvement Plan by Year
2010 - 2020
(As of October 17, 2011)
Location 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
AHS
  • Room 400 ($30,000) (Complete 2011)
  • Boiler ($150,000)
  • Stadium Lights (Complete)
  • Paint ($20,000) (Complete)
  • Green House ($50,000) Complete 2011)
  • Doors ($20,000)
  • Chiller ($250,000)
  • Rebuild Track ($225,000)
HHS
  • Fish House ($70,000)(Complete)
  • Greenhouse ($40,000) (Complete)
  • Replace Marquee
  • Stadium ($200,000)
  • Chiller ($200,000)
  • Gym Bleachers ($60,000)
  • Track ($70,000)
JSBHS
  • Tennis Court ($60,000) (Complete)
  • Roof ($700,000)
  • Green House ($10,000)
  • Stadium ($250,000)
  • Chiller ($150,000)
  • Gym Bleachers ($250,000)
  • Track ($60,000)
PHHS
  • A/C ($40,000) (Complete)
  • Green House ($40,000) (Complete)
  • Gym Floor ($100,000)
  • Backup Boiler ($80,000)
  • Roof ($600,000)
  • Chiller ($80,000)
  • Stadium ($400,000)
  • Gym Bleachers ($120,000)
  • Track ($225,000)
NEFF
  • Roof ($500,000)
DMS
  • Gym Floor ($50,000) (Complete)
  • Carpet ($10,000) (Complete)
  • Carpet ($10,000) (Complete)
  • Restrooms ($20,000) (Complete< 2010)
  • Restrooms ($12,000) (Complete 2010)
  • Roof ($400,000)
  • Doors ($10,000)
EBSMS
  • A/C (40,000) (Complete)
  • Roof ($504,000)
  • Doors ($10,000)
  • Flooring ($20,000) (Complete 2010)
  • Restrooms ($40,000) (Complete 2010)
GSMS
  • Roof (Complete)
  • Gym Floor ($50,000) (Complete)
  • Replace Marquee
  • Chiller ($80,000) (Complete 2011)
  • Replace Picnic Shelter
  • Restrooms ($30,000) (Complete 2011)
  • Paint ($15,000) (Complete 2011)
  • Doors ($10,000)
WMS
  • Flooring ($20,000) (Complete)
  • Flooring ($20,000) (Complete)
  • Lockers ($15,000) (Complete)
  • Roof ($326,000)
  • A/C ($50,000)(Complete 2010)
  • Chiller ($100,000)
AES
  • Restrooms ($30,000) (Complete)
  • Chiller ($70,000)
  • Roof ($300,000)
  • Doors ($12,000)
  • Bleachers ($60,000)
GES
  • Restrooms ($3,000)
  • Gym Ceiling ($10,000) (Complete)
  • Playground ($80,000)(Complete)
  • Treatment Plant ($200,000)
  • A/C / Heat Units ($225,000)
HPES
  • Restrooms ($40,000) (Complete)
  • Restrooms ($40,000) (Complete)
  • Roof($300,000)
  • Chiller ($80,000)
  • Backup Boiler ($110,000)
MES
  • Restrooms ($10,000)
  • Doors ($10,000)(Complete 2011)
  • Waterheater ($6,000)
  • Bleachers ($62,000)
RVES
  • Restrooms ($10,000)
  • Roof ($208,000)
  • Treatment Plant ($200,000)
VIES
  • Playground ($80,000) (Complete)
  • Roof ($120,000) (Complete by Insurance 2011)
  • Flooring ($10,000) (Complete 2011)
  • Treatment Plant ($200,000)
  • Doors ($10,000)
WES
  • Restrooms ($12,000) (Complete)
  • Gym Floors ($55,000) (Complete 2010)
  • Roof ($317,000)
  • Treatment Plant ($200,000)
SBO
  • A/C (Complete)
  • Roof ($50,000)
ANNEX
  • A/C ($40,000) (Complete)
  • Carpet ($30,000)
WAREHOUSE
  • A/C ($10,000)
BUS GARAGE
  • Heat ($10,000) (Complete 2010)
Yearly Budgeted Big Ticket Items: Painting - $50,000; Sports Fields - $30,000; Doors - $20,000; Paving - $100,000; Kitchen Equipment - $55,000; Flooring - $15,000; Roofing - $100,000
Last Update: 2012-01-19 10:34:01